FAQs to the Topic
Survey – Text Version
Virtuelle Endlagerausstellung
Introduction
Waste Quantities / Prognosis
Waste NPP Operating Times
Return of radioactive waste
Morsleben Site
Konrad Site
Gorleben
Asse
Repository Surveillance
Site Selection
BfS Papers on the Topic

Disposal > Waste NPP Operating Times

Waste Prognoses for Different Nuclear Power Plant Operating Times
The prognoses of waste volumes required for repository planning are based on the nuclear power plant operating times of 32 years set out in the provisions of the Atomic Energy Act and on the ban on building new nuclear power plants. This was in correspondence with the “Nuclear Consensus” agreed between the utilities and the federal government in 2000. Thus, a compromise was found between the immediate phase-out in 2000 and unlimited operating times.

In the coalition agreement between CDU, CSU, and FDP of 26 October 2009, the parties declared their willingness to extend the operating times of German nuclear power plants. More detailed regulations are to be set out in an agreement with the operators regarding the conditions for an extension of operating times. Since these regulations have not yet been established, model assumptions for an extension of operating times of 10, 20, and 30 years for all nuclear power plants have been made which are shown in the following.

Waste with Negligible Heat Generation

As regards waste with negligible heat generation, a production of waste of 45 m3 per power reactor and operational year is meanwhile generally assumed. Assuming an extension of operating times of all currently running 17 nuclear power plants by 10, 20, or 30 years, compared with the 32 years of operational time set out in the provisions of the Atomic Energy Act, this would result in the following additional amounts of waste (the values were approximated):

Extension of
 operating time


years
Total amount of additional waste
 (operational waste)


m3

10 Approx.  7,650
 20 Approx. 15,300
30 Approx. 22,950

According to the prognosis on the basis of the Atomic Energy Act stating an amount of waste produced of then 60 m3 per power plant and operational year (operating time 32 years) one would have to expect 277,000 m3 of waste until 2040 (cf. http://www.bfs.de/en/endlager/abfall_prognosen.html). Approx. 60 percent by volume of these arise in the nuclear power plants, the waste from dismantling being the largest portion. Approx. 40 percent by volume originate from other areas, less than 3 % from the federal state collecting depots, among them the waste from medicine (less than 0.5 %).

Spent Fuel Elements

Spent fuel elements with approx. 370 tons of heavy metal (t HM) are produced per year in the currently running 17 nuclear power plants. In the case of changes of operating times the following additional amounts of waste would result (the values were approximated):

 Extension of operating time

years
 Additional spent fuel elements

t HM
 10 Approx. 3,700
 20 Approx. 7,400
 30 Approx. 11,100

The prognosis on the basis of the Atomic Energy Act (operating time 32 years) states 4,800 t HM after January 1, 2009. By the end of nuclear energy use in Germany, altogether 17,400 t HM of spent fuel elements are expected, 10,600 t HM of which are to be directly disposed of  (cf. http://www.bfs.de/en/endlager/abfall_prognosen.html). The volume of this waste is expected to be 21,000 m3. In case operating times would be extended, the amount of spent fuel elements additionally arising would clearly increase according to the above table.

Conclusion

The amount of heat-generating waste, thus, strongly depends on the time nuclear energy will be used. That does not apply to waste with negligible heat generation, as it includes a large portion of waste from dismantling and old waste from the large research institutions going back to the time of the state research projects carried out for introducing nuclear energy in Germany.

Printer safe version